Red Zuma Project

Categories: BusinessTechnology

Part 1

  1. The project is estimated to be completed in 260 working days. The project starts on January 2nd, 2015 and ends on January 8th, 2016.
  2. The critical path for the project is as follows:
    Market Analysis, Product Design, Product Design Selection, Detailed Project Design, Build Prototypes, Field Test Prototypes, Finalized Product Design, Final Manufacturing Process, Order Components, Order Production Equipment, Install Production Equipment, and Celebrate.
  3. The activity that has the greatest amount of slack is Detailed Marketing Plan, of 179 days.
  4. The network is not very sensitive.
  5. One sensible milestone is the Product Design Selection because it is the start of a critical merging activity and completions are used as milestones.

    The completion date for this is 4/3/2015. Another sensible milestone is Finalized Product Design because it is a critical merging activity with a start date of 8/5/2015. The names of activities can sometimes give an idea of how important they are as well.

Part 2A

The resources that are over allocated are marketing specialist, design engineer, industrial engineer, and purchasing agent.

Get quality help now
Doctor Jennifer
Doctor Jennifer
checked Verified writer

Proficient in: Business

star star star star 5 (893)

“ Thank you so much for accepting my assignment the night before it was due. I look forward to working with you moving forward ”

avatar avatar avatar
+84 relevant experts are online
Hire writer

Once the resource leveling is completed, the over allocated resources decrease from 4 to The over allocated problems are design engineer and industrial engineer, with the greatest total slack for detailed marketing plan decreasing. In the end the project task changes in the duration period after resources leveling. The sensitivity of a network continually changing refers to the network diagram after resources leveling. (Include a Gantt chart with the schedule table after leveling within slack.) The project now takes 290 days.

The total duration to complete the project changed and actually increased after resource leveling and made the completion later than the original estimation.

Get to Know The Price Estimate For Your Paper
Topic
Number of pages
Email Invalid email

By clicking “Check Writers’ Offers”, you agree to our terms of service and privacy policy. We’ll occasionally send you promo and account related email

"You must agree to out terms of services and privacy policy"
Write my paper

You won’t be charged yet!

The impact resources can have on a schedule effects directly to project duration time. (Include a Gantt chart with a schdule table displaying free and total slack depicting the resource-constrained schedule.)

Updated: Jul 07, 2022
Cite this page

Red Zuma Project. (2016, Sep 09). Retrieved from https://studymoose.com/red-zuma-project-essay

Red Zuma Project essay
Live chat  with support 24/7

👋 Hi! I’m your smart assistant Amy!

Don’t know where to start? Type your requirements and I’ll connect you to an academic expert within 3 minutes.

get help with your assignment