Revision of Date of Completion of the Project

This is covered under clause 29, which covers the Revision of date of completion of the project. Under clause 29 the JBCC lists events where the contractor is entitled to a revision of date practical completion but is not due compensation and those that the contractor is due compensation, in the case of the JBCC, the value of the contract or project will not change as a result of the listed event. All though this is the case, some of the events listed under clause 29.

1 are covered in section 6, but have different consequences. One such issue is how the different contracts deal with adverse weather effects on works during construction period.

While the NEC contract states the effects of weather on the works as a compensation event under clause 60. 1. 13, where a weather measurement is recorded during a calendar month, before the completion date for the whole of works and at the place stated in the contract data, the weather event must occur less frequently than once in ten years to be a compensation event.

Get quality help now
Bella Hamilton
Bella Hamilton
checked Verified writer

Proficient in: Business

star star star star 5 (234)

“ Very organized ,I enjoyed and Loved every bit of our professional interaction ”

avatar avatar avatar
+84 relevant experts are online
Hire writer

This could mean that should this occur the contractor is due compensation for any costs incurred and a revision of completion time. While the JBCC deals with weather in a different way. In clause 29. states the circumstances where the contractor is entitled to a revision of the completion date but where the principal agent shall not adjust the contract value, are the delays to practical completion caused by various events. One such event, stated in clause 29. 1. 1 is the adverse effects of weather conditions.

Get to Know The Price Estimate For Your Paper
Topic
Number of pages
Email Invalid email

By clicking “Check Writers’ Offers”, you agree to our terms of service and privacy policy. We’ll occasionally send you promo and account related email

"You must agree to out terms of services and privacy policy"
Write my paper

You won’t be charged yet!

This implies that the contractor can not claim for adjustment to contract value due to adverse weather conditions like in the NEC contract. This is one less compensation event that will need to be budgeted for under the JBCC agreement. Another difference in this is under clause 60. 9 of the NEC contract which covers events neither party could account for or prevent which stops the contractor continuing works and is not one of the stated compensation events. While this is covered in the JBCC under clause 29. 1. 4 as an event that neither party could prevent also, it only allows the contractor a revision of date of completion without a revaluation of the project. The JBCC recognizes some events as requiring compensation and others not, while the NEC all the events are seen as compensation events which will require the employer to pay the contractor more money.

In regards to the communication of such events occurring the NEC gives the contractor considerably more time to notify the Project Manager of the possibility of the compensation event occurring. This is stated under clause 61. 3 which gives the contractor a maximum of eight weeks to notify the Project Manager of the event, failing to do so will mean that the contractor will not be entitled to change prices or the completion date. This is only if the Project Manager failed to notify the contractor of the event, if it was the responsibility of the Project Manager to do so.

While in the JBCC also allows for a time period, which gives the contractor more time to claim compensation if any of the events occur that are listed in clause 29. 1 to 29. 3. Under clause 29. 4. 1-3, the contract states that the contractor must notify the principal agent within 20 days of becoming aware of the event and must take all steps to try and avoid it. There is also a 40 day period after which the event has occurred, within which the contractor must alert the principal agent of it occurring or lose out on being able to claim for compensation. This is stated under clause 29. 5 of the contract.

In both contracts these claims are submitted to the project manager, in the NEC and to the principal agent in the JBCC. These claims are investigated by the employer’s agents, clause 61. 4 in the NEC, states that the project manager must decide whether the event occurred as a result of actions taken by the contractor, or has not happened or is not expected to happen, has no effect upon the defined cost or completion date and is not one of the listed compensation events, the project manager may decide that the contractor has no grounds for his claim and deny the contractor compensation.

If the project manger does decide that there are grounds for the claim he notifies the contractor to submit a quotations for the claim. Should the project manager fail to reply the contractor within a week or a longer time period that is agreed upon by both parties, then the claim is viewed to have been accepted by the project manager. The contractor is the free to submit quotations for the claim. While in the JBCC the process is similar, and is covered under clause 29. which gives the principal agent 15 working days of receiving the claim to grant or refuse the working days claimed or revaluation of contract value depending on the basis of the claim. During which time the principal agent shall determine the revised date of practical completion and identify each circumstance and relevant sub-clause and for each event grant or deny the contractors claim. The principal agent must also supply reasons for the decisions he or she has made. But while in the NEC no response by the project manager, the claim is deemed to have been accepted, in the JBCC it is assumed that the claim has been rejected.

This is sated under clause 29. 8, which provides certain cover for the employer should there be a mishap and the principal agent is unable to reply the contractor, unlike in the NEC. In essence the JBCC contract is the better contract on managing the cost of the project along with time constraints. The contract clearly states the events which if they do occur, will require revision of the date of practical completion and also which events will require both a revision of the date and revaluation of the project.

While under the NEC contract the events listed are events that can all be claimed for money by the contractor, which may lead to the employer having to set aside a greater budget for contingencies because of the number of items listed that can be claimed as a compensation event. The better contract that would ease the client’s worries about budget and time constraints is the JBCC principal agreement.

References

  1. JBCC Series 2000 Principal Building Agreement Edition 5. 0
  2. NEC Engineering and Construction Contract
Updated: Jul 20, 2021
Cite this page

Revision of Date of Completion of the Project. (2018, Oct 04). Retrieved from https://studymoose.com/revision-of-date-of-completion-of-the-project-essay

Revision of Date of Completion of the Project essay